June 13th, 2022
After 2 weeks of work, the project had to be paused while we await additional funding. Please note that the Association is 100% committed to see this to the end and we appeal to you all to join us in completing this project. Please see details below.
Project Status:
1) The services of a tractor was engaged, the area cleared and the foundation dig.
2) A Mason Contractor was engaged and the Steel work completed and the foundation casted.
3) Approximately 20ft of the foundation was not dug, as the NWC asked for time to assess pipes in that area and to properly guide us around them.
Cost:
The cost for work already completed is $615,000 which covers the clearing of the land and digging foundation, Mason work and the cost of Material.
Funding:
Thanks to the residents who got involved. We were able to collect $412,500 from the three (3) revenue stream assigned to the project (Block Drive tickets, Cash donations & Collection at the Gate).
The shortfall of $202,500 was funded from the general pool of funds.
Some residents also donated building materials which included blocks, cement and steel.
The Next Step:
The next step of this phase of work will involve the laying of blocks. It is our hope to lay approximately 600 blocks which should take the foundation above ground level up to 4 block height.
Additional Funding Needed:
In order to complete this next step, approximately $170,000 is needed. The response to the Block Drive has been very limited so we are going to rely on you, the good citizens of White Water Meadows, to double up on your contributions so that the cleared area can be closed off.
We are therefore recommending that until the project is completed, the monthly dues contributions be increased to $1,500 monthly. Of which $1,000 will go towards the wall project.
We need everyone on board for this project to be successful.