Good day Residents.
Please see status of our collection effort and project status to date of our wall building project.
Total funding to date is $772,500 of which we have spent $707,250.07 on work done on Stages 1 & 2.
Available cash balance is $65,249.93
The scope of work for Stage 3
Feel free to also donate material or cash to the project as we prepare to restart on September 10th, 2022
The scope of work to be done in:
* Dig 42ft of foundation
* Steelwork for 42ft foundation
* Cast 42ft foundation
* Fill 600 block pockets
* Prepare and Cast 10 columns foot.
Material Needed
* Cement (40 bags)
* Steel (10 Lengths 3/8 inch)
* Steel (15 Lengths 1/2 inch)
* Sand (10 Yrds)
* Gravel (5 Yrds)
Stage 3 Budget – $300,000.00
Your continued support is anticipated.
Peter Hutchinson
Treasurer