Please see estimate for the completion of the next stage of the wall project. As mentioned before this stage will see us laying and filling 1,000 blocks bringing the wall up to a level of 4 feet while we await the approval of the Parish Council.

Material Needed
1) 1,000 blocks – $142,000
2) 40 bags cement – $56,000
3) 5 yds sand – $19,500
*Material Total = $217,500*

Labour
1) Lay 1,000 blocks and fill block pockets @ $11,000 per 100 (to include Labourer)
Labour Total = $110,000

Total Needed $327,500

We thank you all for the contributions you have made so far and urge you to continue to support your hard working Citizens Association while we work with you to have this project completed.

Fact: An average of $40,000 is contributed by residents towards the project through our monthly collection drive.

Much Much more is needed if we are to complete this project before Christmas. Let’s come together and complete this, as there are other projects awaiting our attention.