Wall project

Wall Building Project update Aug 26th, 2022

Good day Residents.
Please see status of our collection effort and project status to date of our wall building project.
Total funding to date is $772,500 of which we have spent $707,250.07 on work done on Stages 1 & 2.
Available cash balance is $65,249.93
 
The scope of work for Stage 3

Feel free to also donate material or cash to the project as we prepare to restart on September 10th, 2022
The scope of work to be done in:

* Dig 42ft of foundation
* Steelwork for 42ft foundation
* Cast 42ft foundation
* Fill 600 block pockets
* Prepare and Cast 10 columns foot.

Material Needed
* Cement (40 bags)
* Steel (10 Lengths 3/8 inch)
* Steel (15 Lengths 1/2 inch)
* Sand (10 Yrds)
* Gravel (5 Yrds)

Stage 3 Budget – $300,000.00

Your continued support is anticipated.

 

Peter Hutchinson
Treasurer